Most grid-tied home solar systems need Small-Scale Embedded Generation (SSEG) registration with your municipality or Eskom before — or as — you commission. Exact portals differ, but the document pack is similar: single-line diagram, NRS-certified inverter, electrician details, metering plan and CoC. This is a generic checklist, not legal advice.
Answer first: Ask your installer to include SSEG paperwork in the quote. DIY portal submissions without the electrical pack usually bounce.
Generic sequence (metros & Eskom distributors)
- Confirm you need SSEG — grid connection almost always yes, even if you plan zero export. See do I need SSEG?
- Pick approved equipment — inverter with valid NRS 097-2-1 type-test; check metro approved lists where published (Cape Town is the strict reference many others echo).
- Site design pack — single-line diagram, DB changes, earthing/SPD notes, battery location, export limit settings if required.
- Submit application — municipal/Eskom SSEG form or online portal; pay application fees if levied.
- Metering — bi-directional or approved SSEG meter often required before export credits.
- Install + CoC — registered person commissions; CoC issued.
- Commissioning / final sign-off — some distributors inspect or require as-built + GreenCard where policy asks.
- Tariff migration — you may move onto an SSEG tariff with different fixed charges; there is still no separate national “solar tax” for registering (mythbuster).
Documents homeowners should see in the pack
| Document | Why it matters |
|---|---|
| NRS 097-2-1 certificate | Utility interface approval for the inverter model |
| Single-line diagram | Shows protection, changeover, metering |
| Installer / electrician registration | Who is accountable |
| CoC | Legal safety certificate for the work |
| Meter change request | Needed for many export / SSEG tariffs |
| As-built / PV GreenCard (if used) | Quality trail for insurers and resale |
Feed-in vs registration
Registration is about safety and grid rules. Getting paid for exports is a separate tariff question — credits are often modest. Design for self-use first; see feed-in / export credits.
Related answers
- Do I need SSEG?
- NRS approved inverters
- How much solar can I connect?
- PV GreenCard
- Blog: SSEG registration
Need a quote that matches this answer? Structured briefs for SA installers — compare designs before you sign.