What are the steps to apply for SSEG registration in South Africa?

Most grid-tied home solar systems need Small-Scale Embedded Generation (SSEG) registration with your municipality or Eskom before — or as — you commission. Exact portals differ, but the document pack is similar: single-line diagram, NRS-certified inverter, electrician details, metering plan and CoC. This is a generic checklist, not legal advice.

Answer first: Ask your installer to include SSEG paperwork in the quote. DIY portal submissions without the electrical pack usually bounce.

Generic sequence (metros & Eskom distributors)

  1. Confirm you need SSEG — grid connection almost always yes, even if you plan zero export. See do I need SSEG?
  2. Pick approved equipment — inverter with valid NRS 097-2-1 type-test; check metro approved lists where published (Cape Town is the strict reference many others echo).
  3. Site design pack — single-line diagram, DB changes, earthing/SPD notes, battery location, export limit settings if required.
  4. Submit application — municipal/Eskom SSEG form or online portal; pay application fees if levied.
  5. Metering — bi-directional or approved SSEG meter often required before export credits.
  6. Install + CoC — registered person commissions; CoC issued.
  7. Commissioning / final sign-off — some distributors inspect or require as-built + GreenCard where policy asks.
  8. Tariff migration — you may move onto an SSEG tariff with different fixed charges; there is still no separate national “solar tax” for registering (mythbuster).

Documents homeowners should see in the pack

DocumentWhy it matters
NRS 097-2-1 certificateUtility interface approval for the inverter model
Single-line diagramShows protection, changeover, metering
Installer / electrician registrationWho is accountable
CoCLegal safety certificate for the work
Meter change requestNeeded for many export / SSEG tariffs
As-built / PV GreenCard (if used)Quality trail for insurers and resale

Feed-in vs registration

Registration is about safety and grid rules. Getting paid for exports is a separate tariff question — credits are often modest. Design for self-use first; see feed-in / export credits.